←  GenEye AI LabsWhite paper  ·  Layer 03 — Infrastructure
Mobile AI Data Centre on Wheels — White Paper · GenEye AI Labs

GenEye AI Labs — White Paper

Mobile AI Data Centre on Wheels

A self-contained, road-transportable 96×B200 GPU data centre with deployable solar, liquid cooling, and battery storage—designed to convert stranded electricity into AI compute anywhere on Earth.

Author: Raj, CEO — GenEye AI Labs September 2026 Version 1.0
Contents
  1. Executive Abstract
  2. Investment Thesis
  3. Product Architecture
  4. Physical Layout & 3D Design
  5. Compute Subsystem
  6. Electrical & Solar Architecture
  7. Liquid Cooling System
  8. Deployment Sequence
  9. CAPEX Breakdown
  10. Operating Costs
  11. Revenue Model
  12. Target Customers
  13. Competitive Landscape
  14. Risks & Mitigation
  15. Scaling Roadmap

01 — Executive Abstract

The global AI compute market is constrained not by GPU supply alone, but by the years-long timelines required to build traditional data centres, secure grid connections, and provision cooling at scale. Grid connection delays routinely stretch 3–7 years. Meanwhile, stranded electricity—at hydroelectric dams, renewable installations, mining operations, and remote industrial sites—sits unused because there is no data centre nearby to consume it.

GenEye AI Labs proposes a fundamentally different approach: manufacture a complete, road-transportable AI data centre inside a 53-foot semi-trailer, drive it to any site with available power and fibre connectivity, deploy solar wings, and begin selling GPU compute within days—not years.

Our first product, the GENEYE-MDC-1, packs 96 NVIDIA B200 Blackwell GPUs (17.3 TB HBM3e), direct-to-chip liquid cooling, 500 kWh LFP battery storage, and 175 kW deployable solar into a single 53-ft trailer with a total CAPEX of $10–12M. At 80% utilization and $5.50/GPU-hour, a single trailer generates approximately $3.7M in annual gross compute revenue against ~$540K in operating costs, yielding a simple payback period of approximately 3.6 years.

96
NVIDIA B200 GPUs
17.3 TB
HBM3e Memory
250 kW
Facility Power Capacity
~$3.7M
Annual Revenue (80% util.)
3.6 yr
Simple Payback Period
Days
Deployment Time

02 — Investment Thesis

The AI infrastructure industry is undergoing a phase transition. Anthropic has committed a reported $35B to Lambda and $45B to Nscale for dedicated AI compute1,2, validating that long-term contracted GPU capacity is the foundation of the next computing era. Yet the fundamental bottleneck has shifted: AI data centres are increasingly a power procurement problem, not merely a GPU procurement problem.

GenEye's mobile data centre inverts the traditional model:

Traditional model: Build $100M+ permanent data centre → wait years for grid connection → deploy GPUs.
GenEye model: Manufacture GPU trailer → drive to site with available power → connect → compute in days.

The Stranded Energy Opportunity

Across the globe, gigawatts of electricity generation capacity sits underutilised—hydroelectric dams in rural Canada, solar farms in the American Southwest, wind installations in Scandinavia, geothermal plants in Iceland, and industrial generation at mining and oil & gas sites. These locations have abundant, cheap electricity ($0.02–$0.06/kWh) but no data centre infrastructure.

Our proposition is direct: find unused electricity, deploy a trailer, connect fibre, and convert kilowatt-hours into GPU-hours. We do not build data centres. We manufacture mobile AI compute infrastructure that follows the energy.

Why Now


03 — Product Architecture Overview

The GENEYE-MDC-1 is a complete, self-contained AI data centre manufactured inside a reinforced 53-foot semi-trailer. Every subsystem—compute, networking, storage, cooling, power, solar, battery, fire suppression, and physical security—is integrated at the factory and road-tested before delivery.

SubsystemSpecificationNotes
Trailer53 ft × 8.5 ft × 9.2 ft interiorReinforced, insulated, vibration-isolated
Compute12 × DGX B200 (8-GPU ea.)96 × B200, 17.3 TB HBM3e
GPU Power~172 kW peak14.3 kW per 8-GPU system
Total Facility Load~213 kW typ. / 250 kW engineeredIncludes cooling, networking, overhead
Networking400/800G InfiniBandNVIDIA Quantum switches
Storage500 TB – 1 PB NVMeHigh-speed local tier
CoolingDirect-to-chip liquid + dry cooler250 kW heat rejection, N+1 pumps
Solar175 kW DC deployableFolding wing arrays + roof panels
Battery500 kWh LFPSolar smoothing, UPS ride-through
Backup Power250 kW grid/generator interfaceAutomatic transfer switch
ConnectivityFibre primary + Starlink backupDual-path redundancy
Fire SuppressionClean-agent + battery-specificDual-zone detection
SecurityBiometric access, cameras, sensors24/7 remote NOC monitoring

04 — Physical Layout & 3D Design

The trailer is divided into three primary zones: Power & Battery (front), Compute Zone A (centre), and Compute Zone B with Networking & Cooling (rear). The following isometric diagrams show the complete system at deployment scale.

GENEYE-MDC-1 — Deployed Configuration with Solar Wings Extended LEFT SOLAR WING — 80 kW RIGHT SOLAR WING — 80 kW POWER ZONE A ZONE B DRY COOLER GENEYE MDC-1 FIBRE POWER IN 53 ft (16.15 m) 9.2 ft Solar PV Trailer Connectivity Power Interface
Fig. 1 — GENEYE-MDC-1 deployed configuration, isometric view. Solar wings extend to ~3× trailer width.
Interior Cutaway — Three-Zone Layout ZONE: POWER & BATTERY UPS 250 kW PDU ATS Transfer SOLAR INV 500 kWh LFP BATTERY BANK BMS + HVAC + Fire Suppression ZONE: COMPUTE A R1 R2 R3 R4 R5 R6 COOLANT DISTRIBUTION MANIFOLD CDU-1 Coolant Dist. Primary CDU-2 Coolant Dist. Redundant IB SWITCH 400/800G Quantum ZONE: COMPUTE B R7 R8 R9 R10 R11 R12 NVMe STORAGE 500 TB – 1 PB FIRE Clean Agent Suppression NETWORK Mgmt Switch Router / FW POWER BUSBAR Cold supply Hot return Power bus GPU sled (8× B200)
Fig. 2 — Interior cutaway, top-down view. 12 racks (R1–R12) each housing one 8-GPU DGX B200 system. Liquid coolant manifold runs beneath racks.
GPU Rack Detail — DGX B200 System with Liquid Cooling 42U COMPUTE RACK TOP-OF-RACK InfiniBand SWITCH NVIDIA DGX B200 8× B200 GPUs | 10U | 14.3 kW max | 313.9 lb B200 B200 B200 B200 B200 B200 B200 B200 NVSwitch — GPU-to-GPU NVLink 5.0 8× 180 GB HBM3e = 1.44 TB per node COLD PLATES HOT RETURN REDUNDANT PSUs — 2× Hot-Swap CABLE MANAGEMENT LOCAL NVMe STORAGE COOLANT QUICK-DISCONNECT MANIFOLD IN OUT To CDU Liquid Cooling Flow B200 GPU + Cold Plate ~1,000W TDP per GPU Hot coolant (45°C) Rack Manifold To CDU Coolant Distribution Unit Heat Exchanger + Pumps (N+1) Primary loop → Secondary loop External Dry Cooler 250 kW heat rejection capacity Roof/rear-mounted — ambient air Cold return (25°C) Heat rejected to atmosphere ↓ ↓ ↓ Total heat load: ~727,000 BTU/hr Coolant: Propylene glycol / water Flow rate: ~200 L/min per CDU Redundancy: N+1 pumps and fans 42U (73.5 in)
Fig. 3 — Single rack detail showing DGX B200 (10U, 8-GPU), cooling manifold, NVMe storage, and liquid cooling flow path from cold plate to dry cooler.
Deployable Solar Wing System — Stowed vs. Deployed TRANSIT MODE ROOF SOLAR — 15 kW (FIXED) WING L — FOLDED WING R — FOLDED → 8.5 ft wide × 13.5 ft high × 53 ft long DOT road-legal dimensions DEPLOYED MODE — 175 kW 80 kW 80 kW ~30 ft deployed width (3× trailer) ☀ 175 kW peak × 25% capacity factor ≈ 43.75 kW avg Feeds directly to GPUs during daylight Excess charges 500 kWh battery
Fig. 4 — Solar wing system: panels fold flat for transit (DOT road-legal), then deploy hydraulically at site to ~3× trailer width.

05 — Compute Subsystem

The compute subsystem is built around 12 NVIDIA DGX B200 systems, each containing 8 B200 Blackwell GPUs. This provides a total of 96 B200 GPUs with 17.3 TB of HBM3e memory—sufficient for large-scale AI training, fine-tuning, and high-throughput inference workloads.

Why Blackwell B200

The B200 represents the current state of the art in AI accelerator design. Each GPU delivers 180 GB of HBM3e at 8 TB/s bandwidth, with support for FP4/FP8 precision that dramatically accelerates inference workloads. The DGX B200 system interconnects 8 GPUs via NVLink 5.0 at 1.8 TB/s bisection bandwidth, enabling the kind of all-reduce operations critical to distributed training.

We selected the DGX form factor specifically because it provides a factory-integrated, tested compute node at a known power envelope (14.3 kW maximum input). This eliminates custom integration risk and provides NVIDIA's full software stack, including Base Command and DGX OS.

10-Year Viability

The trailer is designed for GPU replacement cycles. As next-generation accelerators become available (B300, Rubin, and beyond), the rack infrastructure, cooling, power, and networking can accommodate drop-in upgrades. The liquid cooling manifold uses standard quick-disconnect fittings, and the power distribution supports up to 300 kW peak, providing substantial headroom for denser future GPU nodes.

ParameterPer SystemTotal (12 Systems)
GPUs8 × B20096 × B200
HBM3e Memory1.44 TB17.3 TB
GPU InterconnectNVLink 5.0, 1.8 TB/s—
Max Input Power14.3 kW171.6 kW
Weight313.9 lb~3,767 lb
Form Factor10U120U (+ switches, cabling)
Network Fabric400/800G IB per GPUInfiniBand Quantum

06 — Electrical & Solar Architecture

Load Budget

Load CategoryPower (kW)
GPU Compute (12 × DGX B200)172
InfiniBand / Ethernet Switches8
NVMe Storage4
CDU Pumps5
Dry Cooler Fans12
UPS Conversion Losses5
Lighting / Security / Controls2
Miscellaneous5
Maximum Facility Load~213

The system is engineered for 250 kW continuous / 300 kW peak, providing headroom for transient loads and future GPU upgrades.

Hybrid Power Architecture

The GENEYE-MDC-1 operates as a solar-assisted hybrid system, not a fully off-grid installation. This is an honest engineering distinction: 175 kW of solar at ~25% capacity factor produces approximately 43.75 kW average—roughly 20% of the total facility load. The system is designed to maximise renewable utilisation while maintaining reliable operation through grid or generator backup.

Daytime: Solar feeds GPUs directly; excess charges battery.
Night / overcast: Battery provides partial load + grid/generator supplements.
Low battery: Automatic transfer to grid/generator via ATS.

Fully Off-Grid Option

A customer requiring complete off-grid capability would need approximately 800 kW–1 MW of solar and 2–5 MWh of battery storage. This exceeds a single trailer but is achievable with a dedicated solar field adjacent to the trailer—a viable configuration for remote industrial sites where grid access genuinely does not exist.


07 — Liquid Cooling System

At its ~213 kW typical facility load, the system must reject approximately 727,000 BTU/hour of heat (213 kW × 3,412 BTU/hr per kW). Air cooling is not viable at this density. The GENEYE-MDC-1 uses direct-to-chip liquid cooling throughout.

Architecture

Primary loop: Propylene glycol/water circulates through cold plates mounted directly on each B200 GPU die, absorbing heat at the source. This coolant flows through rack-level manifolds to the CDU.

Secondary loop: The CDU transfers heat through a liquid-to-liquid heat exchanger to the external dry cooler, which rejects heat to ambient air via forced convection.

Redundancy: Dual CDUs (one primary, one standby) with N+1 pumps and fans. The system continues operating with any single pump or fan failure.

ComponentSpecification
Heat Rejection Capacity250 kW (headroom over 213 kW load)
CDU Count2 (primary + redundant)
Cold Plate Inlet Temp~25°C
Hot Return Temp~45°C
Flow Rate~200 L/min per CDU
Dry Cooler PositionRoof/rear-mounted, external
CoolantPropylene glycol / deionised water
Vibration IsolationFlexible hoses + quick-disconnect at every joint

08 — Deployment Sequence

A GENEYE-MDC-1 unit goes from arrival to live AI workloads in a matter of days, not months or years.

Five-Step Deployment

  1. Park & Level — Position trailer on prepared surface. Level using integrated jacks. Secure stabilisation legs.
  2. Deploy Solar Wings — Hydraulically extend folding solar arrays to both sides. Connect DC cabling from wings through weatherproof conduit to internal solar inverters.
  3. Connect Fibre — Plug customer-provided fibre into external patch panel. Establish Starlink backup link. Verify dual-path network connectivity.
  4. Connect Backup Power — Attach grid or generator feed to external power interface (250 kW). ATS verifies all power sources. Battery begins initial charge cycle.
  5. Initialise & Commission — Remote NOC validates all subsystems: GPU health, cooling loop integrity, network throughput, storage, fire suppression, environmental sensors. Begin accepting AI workloads.

09 — Capital Expenditure Breakdown

The following represents planning-grade estimates. Actual procurement pricing, particularly for B200 systems, varies materially by volume, configuration, and supply agreement. GPU servers dominate the economics.

SubsystemKey ComponentsBudget
B200 Compute12× DGX B200, rails, spare PSUs, fans, warranty$5,600,000
NetworkingIB switches, NICs, transceivers, cabling, routers$750,000
Storage500 TB–1 PB NVMe, storage servers, RAID$350,000
Liquid Cooling2–3 CDUs, pumps, heat exchangers, cold plates, dry coolers$650,000
Electrical300 kW transformer, switchgear, PDUs, UPS, ATS, busbars$800,000
Battery500 kWh LFP modules, BMS, PCS/inverter, HVAC$425,000
Solar175 kW PV, folding structures, inverters, deployment mechanisms$450,000
TrailerReinforced 53-ft, raised floor, insulation, racks, vibration isolation$425,000
Fire / SecurityDetection, clean-agent suppression, cameras, access control$175,000
SoftwareGPU monitoring, Kubernetes, Slurm, billing, remote management$300,000
Engineering / Cert.Electrical, mechanical, thermal, structural, transport compliance$600,000
Spares / Contingency~7% contingency reserve$750,000
Total CAPEX~$11,275,000

Working investment number: $10–12M per 96-B200 trailer. GPU servers represent approximately 50% of total CAPEX. As GPU pricing evolves, total unit cost will track accordingly.


10 — Monthly Operating Costs

Assumes deployment at a site with $0.08/kWh electricity, 70% average GPU utilisation, and centralised remote operations (no full-time on-site staff). The headline revenue scenario in §12 models 80% utilisation; the additional draw adds roughly $1,250/month ($15K/year) to electricity, which does not materially change payback.

CategoryMonthlyNotes
Electricity$8,640150 kW avg × 720 hrs × $0.08/kWh
Compute Maintenance Reserve$10,000GPU, PSU, fan, memory, NVMe failures
Cooling Maintenance$1,800Coolant, filters, pumps, dry cooler
Electrical Maintenance$1,400UPS, PDU, switchgear, battery inspect.
Trailer Maintenance$650Tires, brakes, suspension, structural
Solar Maintenance$750Panel cleaning, inverter, deployment hardware
Network / Software$2,750Fibre, monitoring, cloud mgmt, security
Insurance$4,000Equipment, liability, transport
Labour (Centralised)$12,500Infra eng., SRE, NOC, field tech, admin
Miscellaneous$2,500Travel, consumables, permits
Total Monthly OPEX~$44,990
~$45K
Monthly OPEX
~$540K
Annual OPEX

Electricity Sensitivity

Electricity RateMonthly CostAnnual Impact
$0.04/kWh$4,320Saves ~$51K/yr vs. baseline
$0.06/kWh$6,480Saves ~$25K/yr vs. baseline
$0.08/kWh (baseline)$8,640—
$0.10/kWh$10,800Adds ~$26K/yr vs. baseline
$0.15/kWh$16,200Adds ~$91K/yr vs. baseline

Site selection at $0.04–$0.06/kWh electricity provides meaningful cost advantage but does not fundamentally change the unit economics. The dominant variable is GPU utilisation, not electricity.


11 — Revenue Model

Current public B200 pricing provides the benchmark: Lambda lists B200 instances at ~$6.69–$6.99/GPU-hour, while CoreWeave’s equivalent HGX B200 rate is ~$8.60/GPU-hour3,4 (rate cards as of 8 October 2026). We model three price points that position below established providers while maintaining strong unit economics.

Annual Revenue by Price & Utilisation

Maximum annual GPU-hours: 96 GPUs × 8,760 hours = 840,960 GPU-hours.

Utilisation$4.00/GPU-hr$5.50/GPU-hr$7.00/GPU-hr
50%$1.68M$2.31M$2.94M
70%$2.35M$3.24M$4.12M
80%$2.69M$3.70M$4.71M
90%$3.03M$4.16M$5.30M

Unit Economics at Target Scenario

$5.50/GPU-hour, 80% utilisation:

$3.70M
Annual Revenue
$540K
Annual OPEX
$3.16M
Annual Contribution
3.6 yr
Simple Payback

Three Revenue Products

Product A — GPU Cloud
$5–8
per GPU-hour, on-demand or reserved

Customer controls workloads via API. Standard GPU cloud model at a discount to hyperscalers.

Product B — Dedicated Trailer
$250–350K
per month, 3-year contract

Customer leases entire 96-GPU trailer. Private, single-tenant infrastructure on their site.

Product C — Managed AI Infra
$300–500K
per month, full-service

GPU + Kubernetes + storage + model deployment + monitoring + SLA. Turnkey AI infrastructure.

The killer proposition is not "rent our GPUs." It is: "We deploy a private 96-B200 AI data centre at your site in weeks, not years. You supply land + electricity + network. We supply everything else."


12 — Target Customers

Primary Verticals

AI Startups & Scale-ups — LLM companies, video/voice AI, robotics, computer vision, generative media, and AI agent platforms that need hundreds of GPUs but lack the capital or timeline to build their own infrastructure. A mobile trailer provides dedicated capacity without the $100M+ data-centre commitment.

Pharmaceutical & Biotech — AI drug discovery requires massive compute for protein modelling, molecular simulation, and generative chemistry. Lambda publicly cites Iambic Therapeutics using HGX B200 clusters for AI drug discovery. These customers require private, on-premise infrastructure where their data never leaves their environment.

Government & Defence — Military bases, intelligence agencies, emergency response, and government AI laboratories. The value is not cheap GPU-hours; it is: "Bring the compute to us." Security-cleared, air-gapped configurations are possible.

Universities & Research Labs — Researchers with time-limited grants who need burst compute. A 12-month trailer deployment is far faster than a university procurement cycle for permanent infrastructure.

High-Value Verticals

Remote Industrial — This is where the mobile form factor creates genuinely unique value. Oil & gas (seismic analysis), mining (geological modelling), energy (grid optimisation), manufacturing (digital twins), and agriculture (satellite/drone AI) all have electricity and fibre at remote sites but no data centres. That is the sweet spot.

Renewable Energy Operators — Solar farms, wind installations, and hydroelectric facilities with excess generation capacity. We convert their stranded kilowatt-hours into GPU-hours, creating a new revenue stream from existing assets.

Ideal First Customer Profile

A customer with: 250+ kW available electricity, fibre connectivity, physical land, and no data centre—willing to sign a 24–36 month contract at $250K+/month. We deploy. They compute. We do not build the first trailer on speculation. We secure the anchor customer first, then build against the contract.


13 — Competitive Landscape

Competition falls into three tiers: GPU neoclouds (most customers would compare us against these), mobile/modular infrastructure providers, and hyperscalers.

Tier 1: GPU Neoclouds (Direct Compute Competitors)

CompanyPositionB200 PricingThreat Level
CoreWeavePremium GPU cloud, massive scale~$8.60/GPU-hr equiv.
LambdaGPU cloud / clusters, strong brand~$6.69–6.99/GPU-hr
Nscale$45B Anthropic contract, massive infraContract-based
CrusoeEnergy + AI infra (closest thesis)Contract-based
NebiusRapid AI infra expansion~$7.15/GPU-hr
FluidstackDedicated AI computeVaries

Tier 2: Mobile / Modular Infrastructure

CompanyRelevance
AntimatterDistributed/mobile AI infrastructure thesis. Closest emerging competitor to our concept. Watch closely.
VertivTrailer-mounted modular data centres. Infrastructure supplier, not GPU operator.
Schneider ElectricModular DC solutions for remote locations. Infrastructure supplier.
ExyteMobile high-density DC with immersion cooling. Demonstrates concept viability.

Our Differentiation

The trailer itself is not the moat. Any well-funded competitor can put B200s in a truck. The moat is built from six interlocking advantages:

  1. Power acquisition speed — Find cheap/stranded power before competitors.
  2. Days-not-years deployment — Complete AI cluster operational in days.
  3. GPU procurement relationships — Secure NVIDIA supply for B200/B300/next-gen.
  4. Standardised liquid cooling — Proven high-density thermal architecture.
  5. Software abstraction — Customer gets API + Kubernetes, not a truck.
  6. Mobility as optionality — Relocate infrastructure when economics shift.

14 — Risks & Mitigation

RiskSeverityMitigation
Low GPU utilisationCriticalAnchor customer signed before build. 24–36 month contracts.
GPU pricing compressionHighMulti-product revenue (cloud, dedicated, managed). Cost structure allows price flexibility.
NVIDIA supply constraintsHighEarly procurement agreements. Design supports multi-gen GPU drop-in.
Vibration damage during transportMediumVibration-isolated racks, quick-disconnect cooling, factory road testing.
Thermal failures in extreme climatesMedium250 kW heat rejection with N+1 redundancy. Desert/arctic environmental ratings.
Regulatory / transport complianceMediumDOT-compliant dimensions. Battery transport certification. Insurance.
Permanent DC built at same siteMediumMobility: we relocate. Contract terms protect minimum revenue.
Competitive neoclouds at lower priceHighOur value is location flexibility + privacy, not lowest $/GPU-hr.

15 — Scaling Roadmap

Fleet Economics

Each additional trailer is a capital-efficient unit of AI compute capacity. The business scales linearly:

Fleet SizeTotal GPUsFacility PowerCAPEXAnnual Revenue (80% util, $5.50/hr)
1 trailer96~250 kW$11M$3.7M
5 trailers480~1.25 MW$50M$18.5M
10 trailers960~2.5 MW$95M$37M
50 trailers4,800~12.5 MW$425M$185M
100 trailers9,600~25 MW$800M$370M

At 50+ trailers, procurement volume drives unit CAPEX below $9M. At 100 trailers, GenEye would operate a distributed 25 MW, ~10,000-GPU AI infrastructure network—comparable to a mid-sized neocloud, but deployable anywhere electricity and fibre exist.

Phased Build Plan

  1. Phase 1 — Proof of Concept (Months 0–12): Secure anchor customer. Build and deploy Trailer #1. Validate unit economics in the field.
  2. Phase 2 — Initial Fleet (Months 12–24): 5 trailers deployed. Standardise manufacturing. Build operations team and software platform.
  3. Phase 3 — Scale (Months 24–48): 20–50 trailers. Geographic diversification. Next-gen GPU integration (B300/Rubin). Financing products for customers.
  4. Phase 4 — Platform (Months 48+): 100+ trailers. Unified GPU cloud with geographic mobility. AI infrastructure-as-a-utility with locations optimised around global energy prices.

The company GenEye is building is not "mobile data centres." It is mobile AI power-to-compute infrastructure—a platform that finds unused electricity, deploys compute in days, and converts kilowatt-hours into GPU-hours at scale.


Investment Opportunity

GenEye AI Labs is seeking strategic investment to fund the design, manufacturing, and deployment of the first GENEYE-MDC-1 unit, alongside anchor customer acquisition and operational team buildout.

$10–12M
First Trailer CAPEX
$3.7M
Target Annual Revenue
3.6 yr
Simple Payback
$370M
100-Trailer Revenue Potential

For investment enquiries, partnership discussions, or anchor customer conversations:

Raj
CEO, GenEye AI Labs
raj@geneye.ai


Sources & References

Third-party figures cited in this paper are drawn from public reporting and published provider rate cards. All figures are as of 8 October 2026 and are subject to change; GPU rate cards in particular move frequently.

  1. Anthropic – Lambda, $35B (§02). Reported cloud capacity agreement covering approximately 350 MW at a Nueces County, Texas campus under development. Data Center Dynamics, September 2026. datacenterdynamics.com
  2. Anthropic – Nscale, $45B (§02, §13). Reported capacity agreement tied to Nscale’s West Virginia campus; also disclosed in Nscale’s Form S-1. U.S. Securities and Exchange Commission, September 2026. sec.gov
  3. Lambda B200, ~$6.69–6.99/GPU-hour (§11, §13). Published on-demand rate card. Lambda also lists lower rates on single-GPU and 8-GPU node configurations.
  4. CoreWeave HGX B200, ~$8.60/GPU-hour (§11, §13). Derived from the published 8-GPU node on-demand rate of $68.80/hour. Spot capacity is materially cheaper (~$4.26/GPU-hour).
  5. Nebius B200, ~$7.15/GPU-hour (§13). Published rate as of September 2026. Note: Nebius raised its HGX B200 rate to approximately $8.50/GPU-hour effective 1 October 2026, which strengthens rather than weakens the pricing position modelled here.
  6. Iambic Therapeutics on HGX B200 (§12). Customer reference published by Lambda.

GenEye AI Labs is not affiliated with, endorsed by, or partnered with any company named above. They are referenced solely as public market benchmarks.